Thursday, April 23, 2015

Project Management: The Missing Link of Acquisition Reform

codecondo.com
An article published this week on Federal Computer Week highlights the woeful state of the project management capability that currently exists in the federal government, and how attention needs to be paid to this critical government management function.
In the article, Healthcare.gov is once again the punching bag for the model program of what a federal boondoggle is all about. However, lessons learned from this program, along with the Government Accountability Office making Information Technology (IT) acquisition the newest member of their High Risk list , has seemingly given traction to the fact that acquisition reform is a holistic model, and must also include those activities that happen after a contract is awarded.
Former Department of Homeland Security CIO Richard Spires made an excellent point about the focus area:
This is not really a technology problem as much as a skill and cultural one,” he said. “Culture is the biggest issue.
This is an interesting article worth a look, as creating the culture of performance and constant improvement can have a major impact in improving federal programs, especially when it relates to IT.
It is the implementation of the U.S. Digital Services Playbook, along with theTechFAR Handbook, that holds the most promise for turning around federal IT programs through proper use of performance based contracting, and best practices of agile.
The inaugural podcast by Anne Rung, Administrator of the Office of Federal Procurement Policy, highlights successes in IT acquisitions using these prominent procurement tools. The first podcast featured Mark Naggar, project manager of the Department of Health and Human Services' (HHS) Buyers Club. He detailed his use of the TechFAR Handbook and the Digital Services Playbook, specifically noting that he tapped play No. 4, "build the service using agile and iterative practices," to help his team quickly contract with numerous firms for development of IT system prototypes.
The HHS initiative is a great foundation for the art of the possible in government, were engaged and committed leadership demands improved performance from their teams, provide the resources and means to achieve it, and have accountability at the forefront of results.
Combined with effective and agile contracting technique, effective project management can be the critical success factor for programs to succeed. It should be an concerted, integrated effort to address the failures of government management, and not an either/or proposition.

Thursday, April 16, 2015

Basic Steps To Build A Project Estimate


www.saferoutesnj.org
One of the most difficult challenges project managers have in creating the preliminary project package is the Independent Government Cost Estimate (IGCE).

First, what is an IGCE?
According to the Defense Acquisition University:
The IGCE is the Government’s estimate of the resources and projected cost of the resources a contractor will incur in the performance of a contract. These costs include direct costs such as labor, products, equipment, travel, and transportation; indirect costs such as labor overhead, material overhead, and general and administrative (G&A) expenses; and profit or fee (amount above costs incurred to remunerate the contractor for the risks involved in undertaking the contract).
The IGCE will be developed by the requiring activity, and will be used to establish a realistic price or cost for budgeting purposes by the Contracting Officer, in addition to being the baseline for evaluating an offeror’s price/cost proposal. Further, the IGCE will also be used for technical and management information.
Here are some steps and tips for creating your project’s IGCE:
1) Define the Tasks to Estimate
First things first, you will need to determine all the tasks that need to be performed on the project. This can be best accomplished using the Work Breakdown Structure (WBS). Planning tasks by using a WBS allows you to break down the work packages to the lowest level elements for estimating and scheduling resource requirements (people, facilities, and equipment). Further, the WBS can ensure all tasks are identified in terms of cost, schedule, and performance goals in order to reduce risk.
2) Identify Expertise on the Project Team
Hopefully you are working in an Integrated Project Team (IPT), which should be composed of functional experts from the various disciplines needed to manage the project throughout the lifecycle. This diversity will help you estimate and define the tasks, as many of the ultimate tasks will have someone from the IPT allocated to do the work. Once identified, this resource assigned the task is probably the right person to help prepare the estimate.
In the event that IPT members are not the right people, or you are not in an IPT, find someone who can help with the estimate. These individuals ideally have expertise from past experience on similar or like projects. Ultimately, you will need to identify who will create your estimates for every project task. Once you know who will be responsible for helping create the estimates, you can then plan to meet with the right people so you can focus on their sections of the project outside of the typical IPT meetings and the guessing game that often comes with these estimating exercises.
3) Determine the Estimating Technique
Outside of the professional judgment of IPT members or outside the group to help shape estimates and task durations, here are three common techniques:
Analogous estimating. Basing your estimates on the results of a previous project is one the best estimating techniques that project managers can use. If you can find a similar project done in the past, or currently being executed, then you can access the duration of tasks, labor categories used for task estimates, and project budget. Although this estimating technique is efficient, do not fall into the trap of simply cutting and pasting, as this technique may not get you very accurate results.
Parametric estimating. Parametric estimating is a more accurate technique for estimating costs and task durations, as it uses the relationship between variables to calculate the task cost or duration. For example, if it took me two hours to paint a 100 square foot room in my home, and I plan to now paint a 400 square foot room, I could estimate that it will take eight hours to paint.
However, if the first hour were spent prepping the room to paint, the estimate would need to be scaled appropriately: 1 hour for prepping and then four hours to paint, for a total of five hours.
Three-point estimating. This technique allows taking into account uncertainties of estimates, but weights the result more heavily towards the most likely outcome. You will need to determine the most likely, best case, and worst-case timescales for the task. With these figures, add together the durations for the best and worst case, plus four times the most likely. Then divide by six.
The equation:
Best case (O, for optimistic)
Worst case (P, for pessimistic)
Most likely (M, for…. Most)
(O + 4M + P) /6
You can also use this technique for labor costs, especially for labor rates per labor category. One of the best techniques for getting the rates is using the GSA Schedules from GSA Advantage.
4) Track the Accuracy of Estimates - Lessons Learned
Creating estimates is not a one and done exercise. Once they are done, you want to continue to build institutional knowledge by verifying the accuracy of the estimates to determine how well you and the team estimated the task durations and their costs. You should determine whether a particular technique for estimating worked best for your team, or for different types of tasks.
This exercise is for lessons learned, as you will be tracking actuals versus estimates for task durations and costs. Verifying how much time you thought the task would take or cost, and comparing it to how long it really took or cost, is a great way to sharpen your estimating skills to improve on future estimates and to also verify how accurate your estimates were.
Cost estimating is often a difficult exercise, and many project managers have difficulties knowing where to start. These tips should get you on the right path to creating realistic estimates for your project, and avoid the ever-present Atmospheric Estimate.

Wednesday, April 1, 2015

How To Quickly Assess Project Status through Reports

First and foremost, keep it simple. I know I have a tendency to try and over complicate things in reviewing project status. Like many others, we are managing amounts vast amounts of information on our projects (e.g. risks, activities, stakeholders, resources, etc.) and thus need to include everything so nothing gets left behind, right?
Take a deep breath with me, and let’s simply things so we can do what is ultimately or objective: quickly assess project status so we can focus or time. It will help us not only problem-solve, but help us not focus to narrowly such that we miss opportunities to take a look at potential problems and come up with solutions.
Simplification is also important to get collaboration with the project team. If it’s broken down to manageable pieces of work (i.e. tasks due this week), it gets everyone engaged and focused in the same direction, gives resources the opportunity to discuss delivery and potential constraints, helps identify risks, and gets the project focused on the proper path ahead.
So how do we simplify? For starters, only report on exceptions. These exceptions could be in any area, but should revolve around cost, timing, budget, and probably resources or quality. Issues of potential risk are also fair game, as they can eventually lead to delays and overruns. If things are on time and on budget, then great. Focus on current status.
The best way to manage this process is to visualize the data, such as the use of a Gantt chart in Microsoft Project, and subsequently using filters to just see those activities that need to be reviewed (e.g. activities due this week, milestones, etc.) It will help shape the conversation, so focus the status review on just those items, and get everyone board and engaged to ensure that the project follows the plan. Further, this strategy will allow actionable mitigation opportunities to ensure client expectations are met if delays or overruns materialize.
The last thing you want to be doing is going to the customer with problems. Go to the customer with solutions in hand instead. This not only helps build confidence, but the win-win relationships that are needed for success.