Thursday, November 7, 2013
How Healthcare.gov Will Not Drive Federal IT Acquisition Reform
Friday, February 3, 2012
Contract Management 101: A FFP contract is not T&M
However, the contract line item numbers (CLINs) is really where I see performance-based acquisition (PBA) fall off the tracks. This text is straight out of a recent solicitation for a services contract on Federal Business Opportunities, commonly referred to as “fedbizopps” or FBO:
The Offeror shall provide their proposed firm-fixed price for this project by completing the CLIN Listing, in its entirety, as provided in the RFP. Additionally, the Offeror shall also provide a basis for the price, identifying all prospective labor categories, showing labor rates for all labor categories and discounts offered. (The Offerors shall also show profit, and any overhead costs if not included in the labor rate). Lack of detail may result in a rating of a higher risk by the Selection Authority in the selection process.
Significant discounts are considered highly desirable. Discounts offered must be explicit. (There is no page limit for this factor, however Offerors are encouraged to only provide that cost and pricing data mandatory to a comprehensive review and that data which would allow the evaluation team to determine price reasonableness.)Certainly great material to include in my classes when I teach PBA, Contracting Officer Representative (COR), or FAC P/PM courses on how not to structure CLINS under a PBA, or for a Firm Fixed Price (FFP) contract.
For starters, why do you care about this information? You shouldn’t. As a project manager (PM) or COR, you care about performance. Period. The other contract management efforts that will be expended on managing labor rates, labor categories, expenditures, etc. is inappropriate for this contract type, it adds extra administration and complexity into the contract management function, and takes the focus away on what you really care about; performance.
Further, the main objective of a FFP contract is to transfer risk to industry, with the assumption on a FFP contract type that the requirements are clearly defined and baselined. This model wants to eliminate that risk premium, and further drive prices down by threatening to add risk if these factors, which you shouldn’t care about, are not deemed “reasonable?” Protest anyone?
This model is creating a culture of “buying in,” deemed an improper business practice per FAR Subpart 3.5, but now a necessity as a result of budget cuts and the pressure to cut contracts.
PBA is about performance, and incentivizing industry to exceed requirements through a strategic partnership of trust and communication for both parties to excel. Let’s focus on that, and leave the administrative burdens where they belong.
Sunday, October 2, 2011
Performance Outcomes: Judgment Day is Coming
From what I have seen over the last few months and winding up this FY, coupled with the bleak fiscal horizon in the next few years, government operations are in serious trouble. Frankly, if you think government operations are bad now, you ain't seen nothing yet. The Government Accountability Office, Office of Management and Budget, and other watchdog groups and organizations can expect their workload to increase to the point of trying to move a mountain with a shovel.
One only need taking a look at what is happening with alarming regularity, and will no doubt continue as the government continues to find ways to save money and reduce the amount of contractor support and contracted dollars; low price is the only price.
Granted low price, despite illusions of "best value" has always been around, things seem to be spiraling out of control. I have seen with alarming frequency contracts be awarded to low-priced bids, at prices that are ridiculously low compared to both other bidders and government estimates. Sometimes 20% or more below. So much for price not being the most important factor. Price reasonableness and realism? Looking at the bottom-line figure is not enough. Sometimes performance costs money, and should actually save money in the long-run. That is a concept seemingly lost on procurement officials right now.
Although "buying in" is a prohibited practice according to the Federal Acquisition Regulation, it has now become a sanctioned activity. Expect to see many more fixed priced contracts, despite the requirement, in addition to modification after modification. Performance will be an afterthought, as multipliers in industry (the final amount that a contractor bills the government for a dollar of labor, often referred to as “loaded” cost) get lower and lower. Anything less than 2.4 is considered inexpensive; with 2.4 – 2.7 the norm and anything greater than 2.7 considered expensive. I have heard of firms lowering their multipliers to 1.9 to be competitive. Competitive? How can you be profitable?
Size is the answer, as only very large firms can absorb that type of contract strategy. Make it up in volume, and the modification circus that poorly written and "cheap" contracts is also another outcome. This strategy simply decreases competition, especially for small businesses, and will result in even further poor contract performance. Just what we need. Forget about even developing proper requirements, as that is now a cost driver.
So how to you staff these contracts if you are "lucky" enough to win a contract? Answer: on the cheap. Hire know-nothing consultants straight out of college or inexperienced staff to support the requirement, pay them rock-bottom salaries with little if any benefits, and put them through the sausage grinder for a couple of years. Repeat the process. How will government get any decent performance? The current environment and abilities of the acquisition workforce are not conducive for governance and oversight as it is. Now you're going to expect them to provide even more?
Industry: How are you planning to succeed in this environment? What adjustments are you making? What experiences have you had in this "new" low-cost paradigm?
Government: What are you doing to ensure performance with such a low-price? What price reasonableness and realism checks are being done? What technical acceptability checks are being done?
Friday, September 23, 2011
Your Taxpayer Dollar$ at Work: Volume III – Muffin Edition
Of course politicians and the media jumped on the story for easy press, zeroing in on the $16 muffins and nearly $10 cookies served to attendees at one event. Emily Ingram of the Washington Post created a good competitive landscape of the muffin offerings in Washington, and only at government conferences will those prices apply. What is even worse is that DOJ officials basically stated they thought they were addressing the issue:
...Justice officials did not dispute most of the findings. The department did not offer an official to speak by name, but a spokeswoman who was not authorized to comment publicly said the agency “agrees that excessive spending of the types identified in the report should not occur” and has taken steps to prevent it. She said conference costs have been cut this year as part of an effort to curtail nonessential spending, though she could not specify an amount.
Justice Department officials gave auditors a variety of explanations for the expenses, saying consultants they hired to help plan events had valuable knowledge and that the department had done its best to control costs. Officials from one Justice office said they thought they were saving money by serving muffins and other snacks instead of full meals...You're not saving money DOJ, you're wasting it needlessly.
The OIG recommendations are pretty straight forward: itemize costs and ensure you have adequate price analysis to ensure "best value." These controls need to go much further by commoditizing these expenditures, of course itemizing all costs (both direct and indirect), and ensure no surprises and real best-value. There are many other quality, yet reasonable, venues that can accommodate these functions other than the Ritz Carlton.
Adequate market research must be conducted, lessons learned applied, and opportunities for strategic sourcing and leveraging the buying power of the government must be utilized. Further, perhaps this is an opportunity to consolidate BPAs across government and further leverage buying power, in addition to possible using reverse auctions to drive down prices. Cost savings of these types of expenditures are really low-hanging fruit, akin to eliminating free coffee or soda in the break room, which makes this report even more shocking at the level of waste rampant in government.
We obviously have a long way to go in reducing spending, although a thorough spend analysis of these commodity-type of expenditures could probably find millions, if not billions, in needless waste and efficiencies. The opportunities to save money are everywhere. Just look in the snack basket apparently.
Wednesday, August 12, 2009
Coast Guard Moving Forward with Deepwater as SI
In a continued effort to do more with less, a recent report by the Government Accountability Office (GAO) discusses the efforts by the U.S. Coast Guard (USCG) since assuming the role of systems integrator (SI) for the overall Deepwater Program. Admiral Thad Allen has done a tremendous job since assuming his role as Commandant of the USCG, and the GAO report illustrates both the challenges and successes the USCG is having since assuming the SI role, previously held by Northrop Grumman/Lockheed Martin owned Integrated Coast Guard Systems (ICGS).
Understanding that the previous failures in Deepwater were a function of poor management by both ICGS and the USCG, the USCG began its work as the SI by reducing scope, and assigning these functions to Coast Guard stakeholders as significant cost overruns could not be sustained with an existing scope of such magnitude. Further, the USCG has undertaken a fundamental reassessment of the capabilities, number, and mix of assets needed, including finding ways to increase competition and cost reductions by allowing future work on individual assets to be potentially bid competitively outside of the existing contract held with ICGS.
One reason the USCG hired an SI contractor to begin with was in part because of the acknowledgement that it lacked the experience and depth in workforce to manage the acquisition internally. Any chance of success to develop and manage such a vast program such as Deepwater clearly needed outside contractor engagement. Further complicating the issue is the same issue across the federal government; continuing challenges hiring and retaining qualified acquisition personnel with subsequent risks to the successful execution of its acquisition programs. Also like most of the federal government, retooling the acquisition workforce continues in parallel with increased reliance on support contractors to complete the acquisition mission.
The USCG is definitely on the right path, but persistent challenges remain as reported by GAO. Improvements have been made to create a disciplined management process in line with the USCG Major Systems Acquisition Manual (MSAM), but the goal of aligning all Deepwater assets by the end of March 2009 was not reached. One example cited in the report was that operational requirements documents and test plans are not in place for assets with contracts or orders recently awarded (such as the Fast Response Cutter and C4ISR) or in production. This lack of oversight will clearly hinder reaching cost, schedule, and performance objectives.
Budgetary issues are also on the front burner in taking over its programs, and creating budgets and cost schedules on realistic estimates. USCG officials stated the previous baseline determined by ICGS did not reflect a traditional cost estimate, but rather the anticipated contract costs as determined by ICGS. As the USCG continues to develop its own cost baselines, it has become apparent that costs will increase, to the tune of $2.7 billion. I just wrote about the need to create realistic cost estimates, so here is more evidence substantiating that position. As more cost baselines are developed and approved, the USCG can further see the underestimates created by ICGS, and is expecting likely cost growth in its assets. Further revealing how ICGS was managing the program, updates to the asset baselines indicate schedule slips for several of the assets, in addition to finding out that details of their budget submission to Congress at the asset level did not include estimates of total costs and total numbers of assets procured. Although USCG took the GAO recommendations under advisement as they feel they are complying, one area that can be improved is collaboration on major acquisition programs with the Department of Defense (DoD), specifically with budget submission since DoD acquires similar systems and must follow similar processes. Perhaps another example of where social media tools to collaborate and transfer knowledge can be beneficial to improve operations at both agencies.
The USCG is making tremendous strides in how it manages its assets and the Deepwater program, with one of the overarching issues being the continuing need to strengthen its acquisition workforce. The continued application and improvement of the disciplined management processes inherent in the MSAM will also be beneficial to ensure that Deepwater assets are designed and delivered to meet mission needs. Managing Deepwater is not an easy business, but continued oversight and risk mitigation by the USCG will hopefully help continued improvements in managing the largest acquisition ever undertaken by the agency.
Monday, August 3, 2009
Defense Acquisition Reform Needs Common Sense
An interesting piece on defense acquisition reform came out by Scott Reynolds, a professor of program management for the Defense Systems Management College at Defense Acquisition University on how we can come to see poor performance in the defense acquisition process as a matter of fact rather than something that is fundamentality flawed. Although stating that the defense acquisition process is in need of reform is subject to debate, there can be no doubt that the current way of doing business is unsustainable, and that serious consideration has to be given to the way DoD procures goods and services.
…In his book “Knowledge for Action,” Harvard University’s Chris Argyris explains that large organizations like DoD use policy changes as a defense mechanism to avoid embarrassment. As a result, organizations often create policies that hinder improved performance rather than creating workable solutions. A November 2005 Government Accountability Office report highlights that it is not the absence of DoD policy, but Defense’s failure to follow its own policy, that causes most program problems...
Another issue is the problem of cost overruns, which seem ever-present on any major acquisition program and further trickling down to non-major procurement actions as well. The issue here is that dishonesty and unrealistic budgetary estimates are created to allow for a higher chance of actually funding a program, instead of creating realistic estimates that normally would come from an outside entity through an independent cost estimate. Further creating a chain reaction of cost “unrealism” is that industry will further lower their bids from inaccurate funding baselines in an effort to win business. As Mr. Reynolds points out, the government needs creative presentation of finances to get the contract awarded and the program under way, and thus creates a shared lie.
The industry-government partnerships quickly dissolve into contract language discussions instead of product delivery efforts…
The other area of concern described is the revolving door of leadership for major weapon systems. Military officers often rotate out every 2 to 3 years, and thus create an environment of ever-increasing change, increased complexity, and loss of institutional knowledge that often leads to schedule delays and subsequent cost overruns. The rotational assignments for program managers is an issue on many fronts, and will need to be addressed by either finding a way to keep leadership on without destroying careers, or having constant civilian leadership on weapon programs with the military acting in an advisory and oversight capacity.
Tuesday, March 17, 2009
Budgeting for Results
Marvin Sambur, former assistant secretary of the Air Force for acquisition and currently a professor at the University of Maryland, wrote an interesting column about cost overruns and budget issues with defense acquisition programs.
Federal Times.com, March 16, 2009:
…According to DoD rules, before issuing a request for proposal, the services must budget the estimated cost of the program. The estimate process is meticulous, using historical data and managed by a group of costing experts. However, once the winning bid is selected, the service estimate must be replaced by the winning bid number. Since lowest cost is a key factor in determining the winner, all bidders tend to be optimistic in their cost projections. Therefore, the winning number is often too low and cost overruns prevail, when in fact, the original DoD estimates are generally within 3 percent of the final cost…
Mr. Sambur goes on to discuss several rules of budgeting:
…Rule 1. Budgets for program execution should be based on the greater of the program cost estimated by the service or that of the winning bid.
Adherence to Rule 1 prevents the vicious circle that erodes the acquisition process. Each service’s acquisition budget is composed of the summation of the existing programs plus the estimated cost for new programs that will be awarded in the fiscal year. We know from past statistics that these existing programs will likely overrun because the actual cost has been underestimated…
…Rule 2. The winning bidder’s feet must be held to the fire based upon the commitments in his proposal. If the contractor overruns, his future bids should be penalized by adding his overrun percentage to his submitted bid cost. The award fee (if any) should be based upon underruns to the budget determined by Rule 1…
Why can’t DoD hold contractors accountable for their costs? Once the proposal is accepted, this creates the contract. The contractor agrees to provide their solution at the given price proposed. So why has this become so problematic? Several factors are to blame.
First, the government often changes the requirements after contract award, requiring contract modifications and budget overruns. Requirements need to be baselined at contract award and properly managed. Although needs may change, these changes should be carefully reviewed and only approved after a thorough review of impacts on cost, schedule, and performance and by formal channels for such reviews and change requests.
Second, program offices need to ensure proper oversight and budget discipline are integral to effective management of their respective programs. Contractors should be held responsible for ensuring proper cost and program management after contract award, but these important tasks should also be included in their proposal and subsequent contract to hold them accountable.
Third, government personnel, specifically Contracting Officers and Contracting Officer Technical Representatives or COTRs, need adequate training in program management and budget analysis. This includes training in Earned Value Management to ensure cost, schedule, and performance objectives are obtained.
Only through a concerted effort of ensuring accountability and performance will the Government be able to reverse the trend of cost overruns that almost seem inevitable. Mr. Sambur’s common sense approach should be part of any comprehensive acquisition reform discussion.